To view this page ensure that Adobe Flash Player version 11.1.0 or greater is installed.
EDITOR’S CHOICE PROJECTS | ZIMBABWE
reach completion in July 2017. It will be 6 m
in diameter and comprise a four compart-
ment cage with a 3 000 tpd capacity (for
men, material and equipment). The target
will be 1 800 tpd of production hoisting. It
will enable horizon-
tal development
The volume
in two directions
of gold
on two levels (26
ounces Caledonia hopes to produce
from 2021 onwards post the completion and 30 Level)
below 750 m,
of its depth extension programme
ensuring opera-
tional efficiency and re-risking the current
single shaft mine status.
“Our expansion plan will completely change
this mine, guarantee a production ramp-
• Increase underground materials handling:
up to between 76 000 and 80 000 ozpa of
The introduction of a new tramming loop
gold, and secure its long-term future. Our
on 22 Level will increase tramming capacity
next door neighbour is mining well below
(ore and waste) to 2 000 tpd. With a modest
1 000 m, which almost certainly puts us in
$800 000 capital cost, this project has been
the same position to extract ounces well
scheduled for completion by July 2015.
below 1 000 m.”
• Continue No. 6 winze project: Already
Fortunately, Caledonia needs very little
underway, the new vertical shaft provides
investment injected into its process plant,
quick access below 750 m by connecting
which has more than sufficient capacity for
the mine at 630 m below surface to 870
the new production targets.
m. Production from this project will start
Caledonia’s plans for Blanket’s future will
in January 2016 and ramp-up to an extra
ensure a long-life mining operation produc-
500 tpd by mid-2017.
ing significant ounces well into the future. It
• New Central Shaft from surface to 1 080
is not about the immediate or past quarter
m: At a capital cost of $23 million, the
results which have achieved lower-than-ex-
construction of this brand new shaft has
pected volumes and weaker grades (3.6
been scheduled to start in August 2015 and
– 3.8 g/t), but what the company is doing to
80 000 oz
No. 2 conveyor feeds from the primary
surface crushers to the crushed ore stockpile
A revised investment plan, announced in
November 2014, entails an internally funded
three step expansion programme aimed at
accelerating access to deeper resources. An
NI 43-101 independent technical report in-
cluding a preliminary economic assessment
has verified the plan, outlining the results
which include:
• a 267% internal rate of return
• a net present value of the Blanket mine at
$147 million
• of the ounces that need to be produced so
that the cumulative cash flow arising from
the revised plan becomes positive, only 3%
will come from resources that are currently
classified as inferred.
The expansion plan entails three stages:
change that.
TABLE 1 Approximate production from proven and probable mineral reserves above 750 m
(per LOM plan)
Ore from crushed ore
stockpile is fed onto
No. 3 conveyor
Tonnes milled
Gold production
2015 2016 2017 2018 2019 2020 2121
430 000
42 000
460 000
45 000
430 000
43 000
380 000
39 000
230 000
23 000
100 000
10 000
50 000
6 000
TABLE 2 Possible production from inferred mineral resources below 750 m (per PEA)
Tonnes milled
Gold production
430 000
42 000
35 000
4 - 5 000
No. 3 conveyor
discharges onto the triple
deck vibrating screen
above the two secondary
38H Gyratory Crushers.
46 MINING REVIEW AFRICA
| JANUARY 2015
160 000
215 000
390 000
550 000
600 000
20 - 22 000 27 - 30 000 46 - 50 000 63 - 67 000 76 - 80 000