To view this page ensure that Adobe Flash Player version 11.1.0 or greater is installed.
RENEWABLES: LOGISTICS
335 tons abnormal load
on route from Lüderitz to
Northern Cape
From Door to Shore to Site:
The logistic journey of
renewable technology
In conversation with ESI Africa’s content editor Ashley Theron, Chairman Giuseppe Arnoldi of
Global Logistics Alliance (GLA) identifies some of the logistical challenges involved when transporting
utility-scale renewable material from point of pick up to on-site assembly.
H ow does a utility-scale renewable
generation plant physically
come to fruition; what are the
challenges? ESI Africa posed this
question to Arnoldi, placing emphasis on
logistical decisions when setting specific
milestones for a project.
TRANSPORTING “ABNORMAL”
LOADS Concentrated Solar Power (CSP
technology such as steam accumulators,
transformers, heat exchangers etc. are
classified as abnormal items when it
comes to transport and require a detailed
expert blueprint for transportation.
With speed and cost a key priority
for freighting companies, Arnoldi says:
“By way of example, GLA requested that
the shipment of two heat exchangers
from France – expected for delivery
at the KaXu CSP plant in Pofadder in
the Northern Province – be docked in
Lüderitz. Compared to Cape Town or
Saldanha the route is a lot quicker and
if the cargo is shipped to Lüderitz port in
Namibia the road to Pofadder is straight
with limited obstacles such as bridges,
mountain passes, overhead cables etc.
This is a key consideration!”
WHAT TO DO WHEN OBSTACLES
OCCUR? With abnormal loads, freighting vehicles
usually travel no faster than 30km/h. A
route survey is done prior to the project to
scan the environment for any obstacles
such as low lying electrical lines or
low clearance bridges. Should such
ostacles be identified, the local utilities
and telecommunication companies need
to be contacted to temporarily remove
the obstructions. Should a high voltage
line need to be moved the local utility
would need to disconnect it from the
74 230 tons unit on route
from Lüderitz to the
Northern Cape
main electricity grid – this could interrupt
the daily routines within the affected
local community. Therefore clear and
transparent communication with all parties
involved is necessary.
According to Arnoldi, in Keetmanshoop
in the Karas region of southern Namibia,
a 110 meter freighting truck could not
manoeuvre around a traffic circle – the
solution was to build a diversion road.
Another example involved the restructuring
of the Lüderitz port entrance to allow the
heavy load trucks a clear entrance and
exit. The port entrance then had to be
returned back to its original structural size
once the job was completed. The costs
incurred when divergent routes are built
or infrastructure needs to be changed
are initially charged to the party who
requests the route clearance (usually the
transporter), who then bills the client.
PERMITS AND ENGINEERING SKILLS
The entire transport route is precisely
mapped out by a team of qualified
engineers, from the manufacturing
facility up until the installation on-site.
For the purpose of safety, the transporter
does not offload any materials from the
shipping vessels unless supplied with the
engineering drawings, which illustrate the
full details of the cargo such as weight,
dimensions, center of gravity etc.)
A route survey is conducted on the
exact route at least 3-4 months prior to
the operation to identify any obstacles
and possible solutions. During this
survey the transporter will request a route
clearance from the various municipalities
and authorities who will submit these
requests to their engineers.
When transporting very large pieces,
the local municipalities/authorities require
the transporter to purchase a permit.
However, Arnoldi cautions that, for very
large/abnormal items, the acquisition
of permits is currently not regulated.
Negotiations with the relevant authorities
are therefore advisable as there is no
standard pricing in place.
CONCLUSION In order for a power project to be
successful in reaching each milestone,
the logistics requirements need to be
strategically mapped out. With renewable
technology already having high attributed
costs, it is crucial to the project’s budget
that additional costs due to negligent acts
be avoided.
Ultimately, it is the transporter’s
responsibility to map out an ideal route
and in their interests to take all safety
precautions as it is the transporter who
will be held liable for any damages
incurred along the route. ESI
ESI AFRICA ISSUE 2 2015