To view this page ensure that Adobe Flash Player version 11.1.0 or greater is installed.
Jeffreys Bay Wind Farm
Jeffreys Bay wind farm
– how an industry began
The 138 MW Jeffreys Bay Wind Farm, one of the first large
wind energy projects that will be commissioned in South
Africa, stems back to 2001 and a small sustainability related
start-up company.
I n 2001 two individuals, Louis De
Lange and Andries Van der Linde,
had a company called Sudor Eco-
Ventures, which looked at sustainability
in focus areas such as forestry, value-
added agricultural products and water
supply. Van der Linde was based at
the Port Elizabeth Technikon, having
studied overseas and having worked
for a Danish utility. The technikon had a
small wind turbine on its roof and with
his background in Denmark, Van der
Linde started to study wind in the Eastern
Cape. He and De Lange were in close
contact with Eskom in the region and
became aware that a lot of dairy farms
and brick factories in the Hankey,
Patensie, Humansdorp, Jeffreys Bay
area suffered from power quality issues,
sitting as they were at the end of a thin
grid system far from generation sources.
Eskom suggested that if a power project
was undertaken in that area it would be a
good idea.
The decision was made to form
Genesis Eco-Energy, which did a study
that concluded a combination of wind
energy and pumped storage would work
well. A local dairy farmer, Mark Holliday,
was open to the idea as the area needed
the power – dairy farmers were losing
a lot of fresh milk when the power went
down. The plan was for a 10 MW wind
project to be sited on Holliday’s farm
located between Humansdorp and
Jeffreys Bay and a 5.0 MW pumped
storage scheme to be located on the
Gamtoos River. The group brought in
Davin Chown, now director of Genesis
96 Eco-Energy, from the investment and
finance sector, to see if he could source
finance for the venture.
In 2003/2004 a steering committee
for the project formed. It included
members of Eskom, Eddy Leech and
Chris Billingham, the local municipality,
the World Bank which was seeing the
carbon issue raise its head and wanted to
seed development, and the Development
Bank of Southern Africa (DBSA) which
put up some money for an Environmental
Impact Study (EIA) undertaken by the
CSIR. “At the time it was mostly the
Genesis Eco-Energy shareholders that
invested their money into the project and
forged ahead with it,” Chown says.
The plan was to put the electricity
from such a project into the municipal
grid. One of the first municipal power
purchase agreements (PPAs) was
drawn up, the intention being to sign
with the Jeffreys Bay municipality.
However, undertaking a project was
easier said than done. With the nature
of the regulatory framework in place, it
was difficult to get acquiescence from
the National Energy Regulator of South
Africa (Nersa), and the project could not
progress to financial close.
Unlike the Darling Wind Farm project
that was developed by Herman Oelsner,
the Jeffreys Bay Wind Farm team
wanted to keep its project commercial
and private as opposed to turning it into
a government backed demonstration
initiative. While the 5.2 MW Darling
project was built earlier, in the long
run the latter proved to be the more
successful route.
Chown says that the Jeffreys Bay
project was going to use refurbished
turbines which came in at good prices,
because of repowering in Europe. “These
turbines had been up for only eight to
10 years and would have been fine to
test the market within South Africa. We
wanted to get the wind farm up and do
baseline studies. We were also looking
at other sites, on the west coast of South
Africa, in the Northern Cape, and seven
or eight different places in the Eastern
Cape. “For the next five years, from 2004
to 2009, the project moved along slowly.
The regulatory regime was the big
blockage. Doors did not open. A group
called Amatola Green Power had private
clients that wanted power, but it was not
willing to pay wind farm prices.
During that period several parties
were keen on undertaking the project.
Dutch, Greek, and a reputable British
company that is currently active in South
Africa, all looked at it and were excited
but could not see it working because of
regulatory blockages. Nersa said yes
but municipalities could not by law, as
remains the case, because the power
received would be more expensive
than what they get from Eskom. There
was also the issue of how to absorb
the cost of the power on a three year
timeframe according to which municipal
procurement operates.
Between 2002 and 2008, the
undocumented gentleman’s agreement
between Genesis Eco-Energy and Mark
Holliday kept the dream of the wind farm
project alive. “All the landowner asked
was our promise that we would do all we
could to make it work. Holliday said he
ESI AFRICA ISSUE 1 2014